After the transformation of the main building into two sections, connected by air gallery.
改造后建筑主体为两部分,由空中连廊连接。Installation scheme in air was selected for lifting and installing of steel gallery after comparing it with whole lifting method.
比较空中散装方案和整体提升方案后,选择空中散装方案进行连廊钢结构的提升及安装。By using GPZ isolation bearings to weaken the connection of steel gallery, the units of structure become more regular.
通过对连廊节点采用GPZ盆式橡胶隔震支座,弱化主塔楼与裙房的连接,使上部结构单元变得简单规则。Steel truss gallery of Shaoxing World Trade Center 22~24 floors is lifted by integral hoisting technology.
绍兴世贸中心22~24层之间连廊为钢结构桁架体系,安装时采用整体吊装提升技术。The architects made the model themselves (scale 1: 2. 5) to demonstrate the feasibility of the construction, and it's proved successful.
这就是建筑师们为了证明空中连廊可实施性所作的实验模型(比例1:2.5),最终方案得以顺利通过。High-level Integral Rolling-crossing-shifting Installation Technology for a Steel Structure Gallery
钢结构连廊高空整体滚动跨越移位安装技术The Influence of Earthquake Resistance about the Main Steel Structure and Corridor Self with Installing Damper at the Corridor
有阻尼连廊对主体钢结构及连廊本身抗震性能的影响Analysis Of impacts Of Earthquake-Resistance Ability of Main Buildings Made By Additionally Building Air Gallery On High-Rise Building Annex
高层建筑裙房加建空中连廊对主楼的抗震能力影响分析Construction Technology of Flying Scaffold for Cast-in-Place Concrete Floor Formwork for High and Long-Span Steel-Structure Corridor
高空大跨度钢连廊现浇楼面的模板吊架施工工艺